HOME>>               Main Library Catalog>>            Arlington Branch Catalog>>            Bookmobile Catalog>>     

 
w e e k l y    p r o g r e s s    r e p o r t s                             Re-discover Your Library


August Flood Photographs



 Week of May 12, 2008

 


 Week of April 28, 2008

This week we learned a little more about the time line for our major reconstruction work here at FHCPL.  Ryan Guth of Miller Contracting said the interior demolition will begin around May 8th, and the exterior sanitary holding tank work should begin  by the 15th. Structural steel has been ordered, and  the main natural gas line has been excavated near the parking garage entrance.
There will be a new electric transformer located in that same area, and the mid-sized trees growing there will need to be removed. Miller Cont.will be the planning manager, and Ryan should have a project schedule for us in the next few days. He has informed me that the old Community Room will not see demolition work until late June, so the staff will be able to continue using that space for their breaks and lunch for now. --Dick Taylor


 Week of April 21, 2008

Friday, April 18th Dave Hand from subcontractor (Custom Home) was in and explained the
function and design of the new lift for the Technical Services addition. We decided to reverse
the door opening so that it will open back against the brick wall rather than opening out, and
creating a bit of a barrier for users. Cory was able to get all of our excess furnishings moved
to the north end of our parking garage, so that area will be available for contractors to use
and store equipment. We got word from our general contractor that the parking garage will
probably be closed in the first couple of weeks of May, and stay closed thru the duration of
the construction process.--Dick Taylor

 


 Week of April 14, 2008
 

Preliminary work and organizational meetings have been conducted this week as we prepare for the onset of major flood recovery construction in the next two weeks. Our main natural gas feed line has been re-routed by workers from Marlin White, and other workers have begun dismantling some of the HVAC components in the basement. We have decided to close the underground parking garage to all traffic through the major construction phase of this project for safety reasons. Patron and staff parking will be available in our parking lot located on the NW corner of Front St. and Cory St. as well as on Broadway for limited time slots (see signs). Thanks for your continued patience as we strive to provide a flood proof building over the next several months.--Dick Taylor


 Week of April 7, 2008

Work begins on the construction phase of the flood recovery project. Marlin White and Sons Construction began work on the new 4" gas line that will feed the new boilers in the new Mechanical Building on the west side of our building. They had to bore through the Parking Garage Wall, and route the new line over the entrance gate to the Parking Garage. Work also began on the individual HVAC control boxes in the basement level. --Dick Taylor
 

We are happy to report that Construction is now underway. If we need to make changes in the Parking at the Main Library, we will post it here. --Carol Dunn
 


 Week of March 17, 2008

FEMA approved $1,900,311.69 for construction and mitigation efforts. The 75% that FEMA will pay is $1,425,233.77. The State of Ohio will pay 12.5% and FHCPL will have to pay 12.5%. The Board of Trustee's will be meeting on March 18th to approve construction and to accept the FEMA approved and obligated dollars to be used towards the flood recovery project. The construction and mitigation efforts include the reconstruction of the lower level, remodeling of the Community Room to house Administration and Technical Services. The project also includes moving the mechanical systems above the base flood elevation level. We appreciate your understanding and patience during all of the changes.--Kelly Foust


 


 Week of February 25, 2008

The Findlay-Hancock County Public Library (FHCPL) has been working with the Federal Emergency Management Association (FEMA) since President Bush declared the City of Findlay a disaster area on September 11, 2007. Many FEMA representatives toured the building to assess the damage and to assist with the necessary steps to help FHCPL seek funding.

The Ohio Emergency Management Association (OEMA) is currently in the process of reviewing the Project Worksheets from FEMA. OEMA will be turning in the Project Worksheets to Washington for final approval. It is hopeful that Washington will review and approve them fairly quickly. Construction cannot begin until the funds have been approved and obligated to the State of Ohio. After funding is approved, FHCPL will work with the State of Ohio to receive funds as a reimburseable expense at 75%. The State of Ohio will reimburse at 12.5%, leaving FHCPL to pay the remainder.

Project Worksheets are forms to document the scope of the work and the cost estimate for the project. The Project Worksheets supplies FEMA with the information necessary to approve the work along with costs estimates prior to funding the project. FHCPL's Project Worksheet is considered a large project due to the proposed construction and mitigation.

The construction project involves reconstruction of the lower level, adding a floor in the Children's Department above the atrium, adding a floor in the Community Room to accommodate office space for Administration and Technical Services. The project also includes adding a mechanical room elevated at a higher level to lessen exposure (damage and financial) to future floods.  -- Kelly Foust
 


 Week of February 6, 2008

The Main Library closed due to Street Flooding. We received 2 inches of water in the garage, and we have taken on a bit of water in the basement. We are locating the Administration and Technical Services offices upstairs till we go into construction.


 Week of February 4, 2008

Future plans for the lower level include: a designated Volunteer space, a new Community Room and Book Cellar. Charles Construction is the project manager. Morrison Kattman Menze is the architect for the project.


 Week of December 3, 2007

The Main Library has reopened.  We are working with FEMA to mitigate the basement area and our Community Room.
 


 Week of November 5-9, 2007

The Children's and AV departments are being carpeted this week. The library has decided to combine these 2 desks into one and call it the "Information Desk". It will be located in front of the Southwest Window.
 


 Week of October 29-Nov.3., 2007

The staff finish painting the AV Offices and the Computer Lab.  A new floor is being put down in the lobby.

Many caring people have contacted us to offer donations of books. While we much appreciate any offers of assistance, the best way to help your library at this early stage of our rebuilding process is to donate funds.   We will gratefully accept donations to assist with recovery.  You may contribute to the Findlay-Hancock County Public Library Relief Fund at any Fifth Third Bank or send a check to: Fifth Third Bank, 337 South Main Street, Findlay, Ohio 45840.  The Findlay-Hancock County Public Library is funded through the Ohio Library Legislative Fund and does not receive funding via the United Way, the American Red Cross or any other local relief efforts. 


 


 Week of October 22-26, 2007

Children's Storytime is now being held at the Stately Raven Bookstore on Tuesdays and Thursdays at 10:30 a.m. This is open to Children of all ages.  1315 North Main Street, 419-427-2814

Volunteers help move all the Childrens Books and AV materials. New carpeting comes to these 2 departments on November 5th.

Library Book Truck Brigade makes an appearance at the Halloween Parade on October 23.
 


 Week of October 15-19, 2007

New phone system is installed and staff takes training on Voice Mail and the new features.

OPLIN calls the AT&T Engineers and they say we may have Internet service restored as early as mid-November.

Childrens and AV offices are painted a bright and cheery color.


 Week of October 7-13, 2007

New phone system arrives on Wednesday.

Tuesday October 9th: almost 200 patrons show up to check out books at the Arlington Branch Library. 

Library closed on Columbus Day, October 8th. The Book Drop at the Main Library is closed.


 Week of September 30-October 6, 2007

On October 2 Library Board contracts with Charles Construction to restore Lower Level and make improvements.

Inmates from the Hancock County Jail help with stripping old slate and landscaping.

Administration continues to prepare documentation for FEMA. 


 Week of September 23-29, 2007

Library begins to utilize volunteers from the community to help with Flood Recovery.


 Week of September 16-22, 2007

Re-assigned staff members help with clean up, shelve materials and landscaping.


 Week of September 9-15, 2007

Bookmobile and Arlington Branch re-open on September 10.


 Week of September 2-8, 2007

The Board of Trustee's held a public meeting at the Lodge at Riverbend Park on September 5th at 7:30 p.m. The meeting focused on Library Recovery efforts with a nice showing of concerned citizens, Hancock County Genealogy Society Members, retired staff members and Friends of the Library.

The first week of September Library Employees break up into teams and work quickly to establish services at Arlington Branch Library with a temporary Internet Cafe. The SEO Delivery Service is relocated to the Community Room at the Arlington Library, and the Bookmobile gets ready to open in locations around the county and in the library parking lot seven days a week.


 Week of August 26-September 1, 2007 

On August 30 two OPLIN engineers come to the Arlington Branch and re-route the internet so the Branch Library can reopen with internet running straight to Columbus on the T1 line.

The library employees man a booth at the Hancock County Fair August 29-September 3.

WebServer is relocated offsite and www.findlaylibrary.org reestablishes service on the WWW.

Main Library has been stripped of all contents in the lower level including drywall and ceiling tiles. Dehumidifiers are running in the upper level to control mold and save our 6 million dollars worth of library materials.


 Week of August 19-25, 2007 

As the flood receded, the library hired Tri-Weh, a recovery team out of Cincinnati to reclaim the Library.  Over a million gallons of water was pumped from the building in a 2 day period. All services were destroyed or damaged in the flood: furnace, electric, internet, phones, security, paging, fire alarm, sprinkler system etc. This also included the internet at our Arlington Branch, which comes directly through the Main Library in Findlay.

Early Tuesday Morning, on August 21, as much as 9 inches of rain fell over parts of Hancock County. To our East, parts of Wyandot County received 15 inches of rain in a few hours. The Blanchard River began to rise and flooding took place over much of the area.  Twelve library employees showed up for work, and spend most of the day bringing up essential materials from the Lower Level, which included the Clerk Treasurer's Office materials.  The rest of the employees were stuck in their homes with no way out. That evening the entire lower level went under water, and downtown Findlay experienced the worse flood in the city's history.

Monday, August 20 the library closed as usual at 8:30 p.m. A light rain was falling, with no indication of the incredible rainfall that was to happen just hours later.

Back

 

© 2007-2008     Findlay-Hancock County Public Library